CAMP AREA INFRASTRUCTURE WORKS FOR YANBU, NORTH JEDDAH PIPELINES

indir_edited.jpg

Contractor:

Scope Of Work:

Construction Duration:

ARAMCO CO

Contract Date:

TEKFEN CONSTRUCTION INSTALLATION CO INC

Site Laydown, Offices and Labor Camp Mobilization Turnkey Project

5 Month

10.04.2017

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

Total Camp Living Capicity:

12.02.2018

TEK-352-SC-003

108,750 m2

12,545 m2

1100 Persons & SAPMT Office

TEK-352-SC-003-01.png
TEK-352-SC-003-02.png
TEK-352-SC-003-01.png

Project Name:

KHURAIS AREA FACILITIES SATALLITE GAS OIL SEPARATION PLANT (GOSP) PROJECT

indir_edited.jpg

Contractor:

Scope Of Work:

Construction Duration:

ARAMCO CO

Contract Date:

GAMA AL MOUSHEGAH ARABIA LTD

Site Laydown, Offices and Labor Camp Mobilization Turnkey Project

6 Month

25.12.2015

Completion Date:

Contract No:

31.12.2016

KSG-334/SC/006

Total Land Area:

Total Building Closing Area:

249,294 m2

18,005 m2

Total Camp Living Capicity:

948 Persons

006-01.png
006-02.png

Project Name:

DESIGN AND BUILD OF TERMINAL 5 AND RELATED FACILITIES AT KING KHALED INTERNATIONAL AIRPORT

indir.jpeg

Constractor:

Scope Of Work:

TAV TEPE AKFEN AND AL-ARRAB CONTRACTING CO JV

Design, manufacture, supply and installation of a labor camp and all associated facilities, including all related subcontract works to the design & build project of terminal 5 and related facilities at king Khaled international airport strictly in accordance with the clauses,

GENERAL AUTHORITY OF CIVIL AVIATION

Construction Duration:

5 Month

Contract Date:

27.11.2013

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

Total Camp Living Capicity:

08.03.2015

R-13-068-DB-0-SUB-008

33000 m2

12,202 m2

3248 Persons

R-13-068-DB-0-SUB-008-01.png
R-13-068-DB-0-SUB-008-02.png

Project Name:

152 CLINICS AT MAKKAH & JIZAN REGIONS – PHASE 3

Contractor:

Scope Of Work:

MINISTRY OF HEALTH

HAIF – MAPAGUNAL JOINT VENTURE

Includes temporary works, structural works of the clinic building, boundary walls and external structures of one ore more than

Construction Duration:

95 DAYS

Contract Date:

03.06.2008

Completion Date:

Contract No:

04.04.2010

Types Y, B3, A

Project Name:

SHUQAIQ PHASE 2 WATER TRANSMISSION SYSTEM

indir (1).png

Constractor:

Scope Of Work:

Construction Duration:

AZIZ MAPA CONSORTIUM

facilities and Workshops at shuqiaq project.

4 Month

SALINE WATER CONVERSION CORPORATION

Contract Date:

29.12.2007

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

29.07.2008

SQ-SC-07-0008

108,604 m2

12,003 m2

Project Name:

Supply, install, commission and Replacement of old water networks in Riyadh Region

Contractor:

Scope Of Work:

Ministry of Water and Electricity

Ibrahim Al Mofawaz For Contracting Solidarity Company

Supply, install, commission and Replacement of old water networks in Riyadh Region

Construction Duration:

24 Months

Contract Date:

Completion Date:

Contract No:

09.10.2006

04.05.2007

425/50510

Project Name:

THE RIYADH METRO PROJECT

Contractor:

Scope Of Work:

Construction Duration:

HIGH COMMISION FOR THE DEVELOPMENT OF ARRIYADH (SAR)

Contract Date:

FAST CONSORTIUM LLC

Concrete works for DEPOT Line 4 & Line 6

6 Month

16.03.2015

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

31.12.2015

CNTR-CJV-271

26,655 m2

26,655 m2

12- ALFEN KSA PREQUALIFICATION FILE 2022 (sürüklenen).jpg
CNTR-CJV-271-01.png

Project Name:

HARAMAIN HIGH SPEED RAIL PROJECT / S4 MADINAH STAION / PHASE 1 / PACKAGE 2

Official_logo_of_MOH.png

Contractor:

Scope Of Work:

Construction Duration:

Ministry of Hajj

YAPI MERKEZI CONSTUCTION COMPANY

Preparation of temporary site facilities at HHR project area to serve for employees during the execution of project.

7 Month

Contract Date:

03.10.2011

Completion Date:

Contract No:

Total Land Area:

06.05.2012

YMI-ALFEN-HHR-003

62,421 m2

Total Building Closing Area:

Total Camp Living Capicity:

13,876 m2

2000 Persons

YMI-ALFEN-HHR-003-01.png
YMI-ALFEN-HHR-003-02.png

Project Name:

The RIYADH METRO PROJECT

Contractor:

Scope Of Work:

Construction Duration:

HIGH COMMISION FOR THE DEVELOPMENT OF ARRIYADH

FAST CONSORTIUM LLC

Construction and Installation of site offices for Line 4&6

4 Month

Contract Date:

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

08.06.2014

31.12.2014

CNTR-CJV-51

14,985 m2

4,470 m2

This is Office, Mechanical Workshop, Warehouse etc. and Facilities.

Total Camp Living Capacity:

CNTR-CJV-51-01.png
CNTR-CJV-51-02.png

Project Name:

The RIYADH METRO PROJECT

Contractor:

Scope Of Work:

Construction Duration:

HIGH COMMISION FOR THE DEVELOPMENT OF ARRIYADH

Contract Date:

FCC SAUDI LLC 

Construction and installation of site offices for Line 5

4 Months

08.06.2014

Completion Date:

11.10.2015

Contract No:

Total Land Area:

CNTR-CJV-31

32,048 m2

Total Building Closing Area:

4,132 m2

CNTR-CJV-31-02.png
CNTR-CJV-31-01.png

Project Name:

The RIYADH METRO PROJECT

Contractor:

Scope Of Work:

Construction Duration:

HIGH COMMISION FOR THE DEVELOPMENT OF ARRIYADH

FAST CONSORTIUM LLC

Construction and installation of satellite office for 4G1 

6 Month

Contract Date:

19.01.2015

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

08.11.2015

N/L

25,000 m2

3,574 m2

FAST CONSORTIUM LLC-03.png
FAST CONSORTIUM LLC-02.png

Project Name:

YANBU POWER AND DESALINATION PLANT – PHASE3, PROJECT

Contractor:

Scope Of Work:

Construction Duration:

AL-TOUKHI COMPANY/ ARANIAN COMPANY FOR WATER POWER DEVELOPMENT (ACWA) JV

Contract Date:

UNITED COMPANY FOR CARAVANS AND PREHAB HOUSES

CAMP FACILITIES FOR STAFF AND OFFICE

5 Month

12.05.2014

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

03.02.2015

N/L

2,240 m2

5,558.65 m2

yanbu-01.png
yanbu-02.png

Project Name:

SHUQAIQ PHASE 2 WATER TRANSMISSION SYSTEM

indir (1).png

Contractor:

Scope Of Work:

Construction Duration:

AZIZ MAPA CONSORTIUM

Camp facilities at ABAHA project.

5 Month

SALINE WATER CONVERSION CORPORATION

Contract Date:

07.12.2007

Completion Date:

Contract No:

Total Land Area:

29.07.2008

SQ-SC-07-0007

15,000 m2

Total Building Closing Area:

1,990.3 m2

SQ-SC-07-0007-01.png
SQ-SC-07-0007-02.png

Project Name:

SHUQAIQ PHASE 2 WATER TRANSMISSION SYSTEM

indir (1).png

Contractor:

Scope Of Work:

Construction Duration:

AZIZ MAPA CONSORTIUM

Prepare the site temporary facilities at shuqiaq camp area to serve for the employees during the execution of the project.

5 Month

SALINE WATER CONVERSION CORPORATION

Contract Date:

29.09.2007

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

29.07.2008

SQ-SC-07-0006

21,360 m2

6,566 m2

SQ-SC-07-0006-03.png
SQ-SC-07-0006-04.png

Project Name:

The RIYADH METRO PROJECT

Contractor:

Scope Of Work:

Construction Duration:

HIGH COMMISION FOR THE DEVELOPMENT OF ARRIYADH

FCC SAUDI LLC

Construction and installation of satellite office for 4G1

6 Month

Contract Date:

16.04.2014

Completion Date:

Contract No:

Total Land Area:

Total Building Closing Area:

23.10.2014

N/L

6,900 m2

792,73 m2

Metro project-02.png
Metro project-01.png