Ongoing Projects
Project 01
MOYEATH CU ZN PROJECT CIVIL WORKS CONSTRUCTION CONTRACT
Client:
Contractor:
Scope Of Work:
Construction Duration:
Contract Date:
Contract No:
% of direct labor / total labor available:
AL MASANE AL KOBRA MINING CO (AMAK)
AL MASANE AL KOBRA MINING CO (AMAK)
Civil Works, Restricted earthworks, Concrete Works formwork and reinforcement.
11,5 Months
6/5/22
SP0861-C037-3W08-001
50 % / 100
Project 02
GOGINAURI HEPP PROJECT
Client:
Contractor:
Scope Of Work:
Construction Duration:
Contract Date:
Contract No:
% of direct labor / total labor available:
ALTER ENERGY LTD
ALFEN CONSTRUCTION COMPANY
14 Months
9/1/22
50 % / 100